A new request from our clients to install a new toughened glass screen to the reception. This work was to be completed out of hours as to not disturb the normal running of the practice.
- Remove existing screen & dispose of.
- Supply & install new post mounted toughened glass reception screen to existing reception area.
- Toughened glass clear flat 10mm thick with exposed edges polished.
- Posts 48mm diameter satin polished s/s posts with matching clamps & fittings.
- Posts to be hidden fastened to counters & ceiling fixed where possible.
- Supply & install 3 speech transfer units.
- Supply & install 1 lockable sliding hatch TBC 300x350mm or client to confirm.
- Out of hours working – works completed on a Saturday to avoid disruption to the staff/public.