To remove old flooring and replace with new polyflor vinyl. Works carried out for Essex Partnership University NHS Foundation Trust. The Essex Community Adult Eating Disorders Service (CAEDS) is a specialist psychological treatment service commissioned to assess and treat moderate to severe eating disorders.

CAEDS Gray’s Hall, Gray’s.

Duration: 7 working days.

Room 1
• Move existing furniture & re-site (all PCs must be disconnected prior).
• Uplift existing floor & dispose of.
• Latex screed sub floor.
• Supply & install new Polyflor vinyl (colour TBC), heat weld seam joints & silicone seal perimeter.
• Apply new thresholds where necessary.
• Reinstate furniture back on completion of new flooring.

Room 2
• Move existing furniture & re-site (all PCs must be disconnected prior).
• Uplift existing floor & dispose of.
• Latex screed sub floor.
• Supply & install new Polyflor vinyl (colour TBC), heat weld seam joints & silicone seal perimeter.
• Apply new thresholds where necessary.
• Reinstate furniture back on completion of new flooring.

Room 3
• Move existing furniture & re-site (all PCs must be disconnected prior).
• Uplift existing floor & dispose of.
• Latex screed sub floor.
• Supply & install new Polyflor vinyl (colour TBC), heat weld seam joints & silicone seal perimeter.
• Apply new thresholds where necessary.
• Reinstate furniture back on completion of new flooring.

Room 4
• Move existing furniture & re-site (all PCs must be disconnected prior).
• Uplift existing floor & dispose of.
• Latex screed sub floor.
• Supply & install new Polyflor vinyl (colour TBC), heat weld seam joints & silicone seal perimeter.
• Apply new thresholds where necessary.
• Reinstate furniture back on completion of new flooring.

EPUT. Gray’s Hall – Polyflor vinyl flooring replacement