Project: Full refurbishment to science labs – stripping out existing lighting, plumbing, worktops, flooring and full redecoration to the classroom.
Budget:
Timescale: – 4 weeks (incl. corridor redecoration work)

Construction Notes:

  • Removal of existing ceiling grid to install new lay in ceiling tiles into new ceiling grid.
  • Removal of existing strip lights from classroom and installation of new design with LED lights into new ceiling grid.
  • Existing flooring removed then supply and install new Polysafe vinyl flooring with a range of colours chosen by client.
  • Existing work benches removed and disposed in licensed waste station.
  • Disconnected existing gas outlets & water taps from worktops and reinstated back into new locations following new classroom design layout by CSF once new Trespa worktops were installed.
  • Supply & install of new Trespa worktops with various colours chosen by client.