Project: Convert Arjo Bath Therapy Room to Physio Room
Duration: 7 days
Description
• Isolate services.
• Remove & dismantle ARJO Bath & toilet.
• Uplift existing flooring including coved skirting & dispose of.
• Supply & install new Altro Whiterock Satins with welded joints.
• Supply & install new suspended ceiling with Hygienic wipeable tiles.
• Supply & install new 600×600 LED light panels.
• Supply & install 3no DSO (double socket outlets), location in room TBC.
• Supply & install new Polysafe Vogue Ultra vinyl with cove skirting.
• Works carried out in a live ward, works completed within 7 days.
Farnham Hospital – Bath Therapy Room conversion to Physio Room