Project: South Lewisham Health Centre refurbishment works
Budget: £120,000
Timescale: 6 weeks (Jan 2017 – Feb 2017)

Construction Notes:
The works carried out and completed were to create 2 new consulting rooms, 2 new patient rooms, 1 new minor surgery room, 1 new dirty utility room, and 1 new treatment room from existing various rooms. This work consisted of:

  • Demolishing walls/Creating new walls
  • New IPS mounted wash hand basins
  • New sluice installed in dirty utility room
  • Electrical plastic dado trunking with necessary double socket outlets & data points
  • Examination lamps installed in minor surgery & treatment rooms
  • New mechanical extract ventilation system via the roof
  • Installing & relocating new panic release buttons
  • UPVC windows & doors
  • Full decoration to all rooms & new Polysafe vinyl flooring with cap & cove skirting

All works were completed whilst the health centre was open to the public and in a live environment with polythene protection and H&S notices where necessary.