Harris Primary School (Crystal Palace) – Hall Project. 2019

Brief of works completed:

Protect flooring & electronic white board.

Isolate, disconnect & remove all emergency light fitting & fire alarm containment, wiring & fittings ready to be replaced on completion of other works.

Erect mobile tower.

Cut out ceiling, baton out ready to take 12no 300×300 fire rated access hatches so gain access to new LED light fittings recently installed.

Remove large wallpaper from hall end & dispose of

Remove pegboard from high level entrance end & dispose.

Make good pegboard with plasterboard, tape & joint ready for decorations.

Rub down & prepare walls, ceiling radiators ready for decorations.

Apply 2 coats of Crown clean extreme emulsion (colour TBC) to walls.

Make good holes in ceiling.

Apply 2 coats of Crown white emulsion to ceiling.

Apply 1 undercoat & 1 top coat to 7no old type radiators & 2no LST.

Dismantle tower, remove protection & leave clean & tidy once complete.


Harris Primary School (Crystal Palace) – Hall Project. 2019