Renovation of 8 classrooms – 1st floor. To be completed in 2 weeks

• Remove furniture, desks & chairs from classrooms & place in safe location.

• Place polythene to cover screens & any electrical items.

• Rub down & prepare walls & woodwork ready for decorations.

• Rub down & prepare existing ceiling ready for decorations.

• Apply 2 coats of Dulux white emulsion to entire ceiling.

• Apply 2 coats of Dulux Diamond matt emulsion to walls.

• Apply 1 undercoat & 1 top coat to skirting & door frames.

• Sand down existing window boards ready to accept 2 coats of clear varnish.

• Uplift existing carpet & dispose of as in poor condition.

• Apply suitable tackifier to accept new carpet tiles.

• Supply & install new Heckmondwike carpet tiles (grey) to each classroom.

• Replace all furniture back into each classroom & leave clean & tidy ready for handover.